Well 152 Design & Construction (District Headquarters)

This project supports the District’s long-term strategy to increase groundwater production capacity and enhance system reliability. Well 152 will be designed, drilled, and equipped at the District’s headquarters property. Once completed, it will provide an additional local water supply source to help meet demand and reduce dependence on imported water. Project completion is targeted for June 2028, with phased efforts including design, permitting, and construction over the next several fiscal years.

Project Type

Water

Current Phase

Design & Construction

Estimated Completion

June 2028

Total Project Cost

$4,950,000

Lake at a facility rental at EVWD

Project Milestones

Project Start

September 29, 2025

Phase 1

Locating Existing Utilities

Current Phase

Phase 2

Water Main Replacement and Fire Hydrant Installation

Phase 3

Street Pavement Repairs

Phase 4

Street Pavement Repairs

Project FAQs

This project supports the District’s long-term strategy to increase groundwater production capacity and enhance system reliability. Well 152 will be designed, drilled, and equipped at the District’s headquarters property. 

This project supports the District’s long-term strategy to increase groundwater production capacity and enhance system reliability. Well 152 will be designed, drilled, and equipped at the District’s headquarters property. 

This project supports the District’s long-term strategy to increase groundwater production capacity and enhance system reliability. Well 152 will be designed, drilled, and equipped at the District’s headquarters property.